To
order by phone:
(801) 374-6214 To order by fax: (801) 374-0634 To order by email. or for questions: Click here.
|
351.1R-99
This report provides an overview of current practices of grouting for support of equipment and machinery. Materials and installation methods are described for hydraulic cement and epoxy grouts used as the load-transfer material between equipment bases and their foundations. Characteristics of placed material, test methods for forecasting long-term performance, qualification of grout materials, foundation design and detailing considerations, and installation procedures are described. A listing of standard test methods and specifications is also included. Contents: 1.1-General 1.2-Definitions 1.3-Grout requirements 1.4-Evolution of materials
2.1-General 2.2-Hydraulic cement grout 2.3-Epoxy grouts
3.1-General 3.2-Hydraulic cement grouts 3.3-Epoxy grouts
4.1-General 4.2-Hydraulic cement grouts 4.3-Epoxy grouts 4.4-Performance evaluation test
5.1-General 5.2-Machine or equipment bases 5.3-Concrete foundation 5.4-Anchorage design 5.5-Clearances
6.1-General 6.2-Anchor bolt 6.3-Concrete surface preparation 6.4-Metal surfaces 6.5-Formwork 6.6-Safety and handling of epoxies
7.1-Consistency 7.2-Temperature 7.3-Mixing 7.4-Placing 7.5-Removal of excess material
8.1-Hydraulic cement grouts 8.2-Epoxy grouts
9.1-General 9.2-Hydraulic cement grouts 9.3-Epoxy grouts 9.4-Documentation
10.1-Recommended references |
ACI
|